For extensively cooperation program between JSC Technical Solutions energy - PTS and Schneider Electric, PTS has signed contract dated 28/03/2016 with Power Transmission Company No.2 on supplying materials, equipment and services for Package 04: “Supplying and transportation of secondary materials and equipment” of Project: “Ngu Hanh Son 220kV substation and Da Nang-District No.3 (Ngu Hanh Son Distric) 220kV line with the contract value of VND 22.102.700.800.

 

 

PTS will use substation automation products of Schneider in this contract, in which, Schneider will supply control relays MICOM, BCU, substation control software PACIS and support services.

Ngu Hanh Son 220kV substation is invested by National Power Transmission Corporation and managed by Power Transmission Company No.2 on the basis of upgrading existing Ngu Hanh Son 220kV substation and Da Nang-District No.3 (Ngu Hanh Son Distric) 220kV line.

Scale of this substation including 02 220kV transformers of 125 MVA (01 transformer for this stage); 03 220kV feeders, 04 110 kV feeders; upgrading control and protection system for the whole substation; adding 6.6 km 220kV line (including  3.31 km of 4-circuit line, 02 220kV circuits, 02 110kV circuits in only 1 pole) and 2.45 km of 110kV underground cable from Tuyen Son bridge to substation.

Ngu Hanh Son 220kV substation is estimated to operate in the third quarter of year 2016.

 

 