Central Power Corporation (EVNCPC) energized and accepted 220kV Phuoc Son substation at 16h00 and 220kV Nhon Hoi substation at 18h00 on 27th December, 2013 in Binh Dinh province. Mr. Thai Van Thang – Deputy General Director of EVNCPC led these activities.

d9e79c75cbe02dbe74f1

Computerized system acceptance test

Phuoc Son 110kV substations, Nhon Hoi 110kV Substation and branch project in Quy Nhon City, Binh Dinh Province started on 29th November, 2012. Phuoc Son 110kV substation and branch has a capacity of 1x25MVA (2x25MVA when completed) at the voltage of 110/22kV; 110kV double circuit with 0.2km length, located at Phuc Son village, Phuoc Son commune, Tuy Phuoc district, Binh Dinh Province. Nhon Hoi 110kV substations and branch has a capacity of 1x40 MVA - 110/22kV (2x40MVA when completed); 1 circuit 110kV line (with design of 2 circuit column) with 26km length, located at K4 area, A plot of Nhon Hoi Economic Zone invested by Saigon - Nhon Hoi Economic Zone Joint Stock Company.

20131226 14050120131227 105201

Quy Nhon - Nhon Hoi 110kV Line goes through Quy Nhon City area (including Phu Tai Economic Zone, Tran Quang Dieu Ward, Nhon Hoi Commune) and Tuy Phuoc Commune (including Dieu Tri town, Tuy Phuoc town, Phuoc An commune, Phuoc Loc commune, Phuoc Hiep commune, Phuoc Son commune, Phuoc Nghia commune and Phuoc Hoa commune).

20131226 182725     20131226 182656

Total investment of the both project is VND 313 billion (Phuoc Son Project is VND 63 billion and Nhon Hoi project is VND 250 billion), of which loans of the World Bank (WB) is VND 235 billion; counterpart funds is VND 78 billion. The goals of the project are to supply power for living, industrial area in Tuy Phuoc District, Nhon Hoi Economic Zone and surrounding areas, and connecting among 110kV substations as well (Nhon Hoi 2 substation, Nhon Hoi 3 substation, Nhon Hoi 4 substation) that will be invested in the future in accordance with the approved plan, to meet growing demand, especially for Nhon Hoi Economic Zone and facilitate economic development for the local, simultaneously, improve transmission capacity and power supply, improve reliability and flexibility of power distribution system as well as the efficient use of electricity.

20131227 15293020131226 182546

PTS Jsc., in collaboration with the relevant units system accepted successfully control and protection panels system for 110kV feeders and transformers, 22kV panels, AC/DC system, telecommunication system and integrated computerized control system.